If the variations in the investment plan implementation among the seven main categories are above 20%, but the overall budget does not change, is it possible to amend the budget?

If the variations in the investment plan implementation among the seven main categories are above 20%, but the overall budget does not change, is it possible to amend the budget?

The budget categories may be amended, provided that the amount of the investment plan’s total budget does not change and the request for amendment is made before the expiration of the investment plan.